If 3 workers complete a task in 12 days, how many workers are needed to complete it in 4 days?

A. 6
B. 8
C. 9
D. 12

Solution:
Work = 3×12 = 36 worker-days.
Required workers = 36 ÷ 4 = 9.
Answer: C.